Silo Storage Tank Vessel
Oil, gas and storage · Bekasi · 2025
Project overview
Silo Storage Tank Vessel in Bekasi is a MAKEPaint project reference for industrial tanks and vessels.
- Location
- Bekasi
- Sector
- Oil, gas and storage
- Project year
- 2025
- Duration
- 11 weeks
- Area
- ± 19,500 m²
- Surfaces
- Tanks and silos
- MAKEPaint products
- 3 products
Project photos
Photos from the project site, by coated surface.
Challenge, solution and result
The conditions on site, the coating system chosen, and how the work turned out.
Challenge
A tank lining is in direct contact with what it holds while the outside faces the weather, so the coating must resist chemicals and seal without gaps.
Solution
A three-coat epoxy phenolic lining: MAKE 613 at 125 µm, MAKE 610 at 125 µm and MAKE 608 at 100 µm, 350 µm in total over SSPC SP 5/10.
Result
An area of about 19,500 m² was coated in 11 weeks. The thickness of every coat was checked on site before handover.
Coating system specification
The MAKEPaint products for each surface, from primer to finish, with the dry film thickness the application guide sets.
| Function | Product | DFT |
|---|---|---|
| Tanks and silosSurface preparation: SSPC SP 5, 10 | ||
| Primer | PrimerMAKE 613Epoxy Phenolic | 125 µm |
| Finish | FinishMAKE 607High Build Epoxy Primer | 125 µm |
| Finish | FinishMAKE 608Multipurpose HB Polyamide | 100 µm |
| Total dry film thickness | 350 µm | |
Project schedule
The stages of the work by week, from the site survey to handover.
Survey and surface tests
Week 1
The technical team checks the surface, the exposure and the area on site.
System recommendation
Weeks 1–2
The coating system and colors are agreed, with samples and technical data sheets.
Production and delivery
Weeks 2–3
The material is made and shipped from the MAKEPaint plant in Cikarang.
Preparation and application
Weeks 3–10
The surface is prepared, then primer, intermediate and finish coats go on.
Inspection and handover
Week 11
Coat thickness and adhesion are checked before the work is handed over.
Survey and surface tests
Week 1
The technical team checks the surface, the exposure and the area on site.
System recommendation
Weeks 1–2
The coating system and colors are agreed, with samples and technical data sheets.
Production and delivery
Weeks 2–3
The material is made and shipped from the MAKEPaint plant in Cikarang.
Preparation and application
Weeks 3–10
The surface is prepared, then primer, intermediate and finish coats go on.
Inspection and handover
Week 11
Coat thickness and adhesion are checked before the work is handed over.
Project video
Coating work on site, from surface preparation to the final coat.
Related documents
Brochures and the catalog for the products used on this project.

Have a similar project?
Tell our team about your surface conditions and requirements.
or email sales@makepaint.co.id