Jalur Sepeda
Infrastructure · DKI Jakarta · 2024
Project overview
Jalur Sepeda in DKI Jakarta is a MAKEPaint project reference for traffic and road markings.
- Location
- DKI Jakarta
- Sector
- Infrastructure
- Project year
- 2024
- Duration
- 10 weeks
- Area
- ± 18,000 m²
- Surfaces
- Roads and car parks
- MAKEPaint products
- 3 products
Project photos
Photos from the project site, by coated surface.
Challenge, solution and result
The conditions on site, the coating system chosen, and how the work turned out.
Challenge
Markings must stay visible day and night, resist tyre wear, and dry fast so traffic can reopen soon.
Solution
MAKE Metroline road marking paint, solvent or water based, and MAKE Line thermoplastic for thicker, longer-lasting lines.
Result
An area of about 18,000 m² was coated in 10 weeks. The thickness of every coat was checked on site before handover.
Coating system specification
The MAKEPaint products for each surface, from primer to finish, with the dry film thickness the application guide sets.
| Function | Product | DFT |
|---|---|---|
| Roads and car parks | ||
| Finish | FinishMAKE METROLINE SBMAKE METROLINE SB | Per TDS |
| Finish | FinishMAKE METROLINE WBMAKE METROLINE WB | Per TDS |
| Finish | FinishMAKE LINE THERMOPLASTICMAKE LINE THERMOPLASTIC | Per TDS |
Project schedule
The stages of the work by week, from the site survey to handover.
Survey and surface tests
Week 1
The technical team checks the surface, the exposure and the area on site.
System recommendation
Weeks 1–2
The coating system and colors are agreed, with samples and technical data sheets.
Production and delivery
Weeks 2–3
The material is made and shipped from the MAKEPaint plant in Cikarang.
Preparation and application
Weeks 3–9
The surface is prepared, then primer, intermediate and finish coats go on.
Inspection and handover
Week 10
Coat thickness and adhesion are checked before the work is handed over.
Survey and surface tests
Week 1
The technical team checks the surface, the exposure and the area on site.
System recommendation
Weeks 1–2
The coating system and colors are agreed, with samples and technical data sheets.
Production and delivery
Weeks 2–3
The material is made and shipped from the MAKEPaint plant in Cikarang.
Preparation and application
Weeks 3–9
The surface is prepared, then primer, intermediate and finish coats go on.
Inspection and handover
Week 10
Coat thickness and adhesion are checked before the work is handed over.
Project video
Coating work on site, from surface preparation to the final coat.
Related documents
Brochures and the catalog for the products used on this project.

Have a similar project?
Tell our team about your surface conditions and requirements.
or email sales@makepaint.co.id