Cerobong PT. Growth Java Industry
Energy and power · Cirebon · 2022
Project overview
Cerobong PT. Growth Java Industry in Cirebon is a MAKEPaint project reference for equipment exposed to high temperatures.
- Location
- Cirebon
- Sector
- Energy and power
- Project year
- 2022
- Duration
- 6 weeks
- Area
- ± 2,500 m²
- Surfaces
- Hot surfaces
- MAKEPaint products
- 3 products
Project photos
Photos from the project site, by coated surface.
Challenge, solution and result
The conditions on site, the coating system chosen, and how the work turned out.
Challenge
Stacks, exhausts and hot equipment run at temperatures that make ordinary paint blister and peel.
Solution
MAKE 303 FT zinc silicate primer at 65 µm with a heat-resistant finish for the working temperature: MAKE 200 up to 200°C, MAKE 400 up to 400°C or MAKE 600 up to 600°C.
Result
An area of about 2,500 m² was coated in 6 weeks. The thickness of every coat was checked on site before handover.
Coating system specification
The MAKEPaint products for each surface, from primer to finish, with the dry film thickness the application guide sets.
| Function | Product | DFT |
|---|---|---|
| Hot surfacesSurface preparation: SSPC SP 5, 10 | ||
| Primer | PrimerMAKE 303Inorganic Zinc Silicate Primer | 65 µm |
| Finish | FinishMAKE 200Silicone Acrylic Heat Resisting Finish | 40 µm |
| Finish | FinishMAKE 400Silicone Heat Resisting Finish | 30 µm |
| Total dry film thickness | 135 µm | |
Project schedule
The stages of the work by week, from the site survey to handover.
Survey and surface tests
Week 1
The technical team checks the surface, the exposure and the area on site.
System recommendation
Weeks 1–2
The coating system and colors are agreed, with samples and technical data sheets.
Production and delivery
Weeks 2–3
The material is made and shipped from the MAKEPaint plant in Cikarang.
Preparation and application
Weeks 3–5
The surface is prepared, then primer, intermediate and finish coats go on.
Inspection and handover
Week 6
Coat thickness and adhesion are checked before the work is handed over.
Survey and surface tests
Week 1
The technical team checks the surface, the exposure and the area on site.
System recommendation
Weeks 1–2
The coating system and colors are agreed, with samples and technical data sheets.
Production and delivery
Weeks 2–3
The material is made and shipped from the MAKEPaint plant in Cikarang.
Preparation and application
Weeks 3–5
The surface is prepared, then primer, intermediate and finish coats go on.
Inspection and handover
Week 6
Coat thickness and adhesion are checked before the work is handed over.
Project video
Coating work on site, from surface preparation to the final coat.
Related documents
Brochures and the catalog for the products used on this project.

Have a similar project?
Tell our team about your surface conditions and requirements.
or email sales@makepaint.co.id