Kapal Golden Tuna
Marine · Bali · 2022
Project overview
Kapal Golden Tuna in Bali is a MAKEPaint project reference for marine surfaces.
- Location
- Bali
- Sector
- Marine
- Project year
- 2022
- Duration
- 4 weeks
- Area
- ± 12,000 m²
- Surfaces
- Ships and boats
- MAKEPaint products
- 3 products
Project photos
Photos from the project site, by coated surface.
Challenge, solution and result
The conditions on site, the coating system chosen, and how the work turned out.
Challenge
A hull sits in seawater, takes impacts and gathers marine growth, so it needs a system that resists corrosion and fouling.
Solution
A four-coat hull system: MAKE 303 FT at 65 µm, MAKE 618 ZP at 50 µm, MAKE 601 at 100 µm and MAKE 500 antifouling at 50 µm, 265 µm in total.
Result
An area of about 12,000 m² was coated in 4 weeks. The thickness of every coat was checked on site before handover.
Coating system specification
The MAKEPaint products for each surface, from primer to finish, with the dry film thickness the application guide sets.
| Function | Product | DFT |
|---|---|---|
| Ships and boatsSurface preparation: SSPC SP 3, 6, 7, 10 | ||
| Primer | PrimerMAKE 303Inorganic Zinc Silicate Primer | 65 µm |
| Finish | FinishMAKE 604Epoxy Tie Coat | Per TDS |
| Finish | FinishMAKE 500Conventional Antifouling | 50 µm |
Project schedule
The stages of the work by week, from the site survey to handover.
Survey and surface tests
Week 1
The technical team checks the surface, the exposure and the area on site.
System recommendation
Weeks 1–2
The coating system and colors are agreed, with samples and technical data sheets.
Production and delivery
Weeks 2–3
The material is made and shipped from the MAKEPaint plant in Cikarang.
Preparation and application
Week 3
The surface is prepared, then primer, intermediate and finish coats go on.
Inspection and handover
Week 4
Coat thickness and adhesion are checked before the work is handed over.
Survey and surface tests
Week 1
The technical team checks the surface, the exposure and the area on site.
System recommendation
Weeks 1–2
The coating system and colors are agreed, with samples and technical data sheets.
Production and delivery
Weeks 2–3
The material is made and shipped from the MAKEPaint plant in Cikarang.
Preparation and application
Week 3
The surface is prepared, then primer, intermediate and finish coats go on.
Inspection and handover
Week 4
Coat thickness and adhesion are checked before the work is handed over.
Project video
Coating work on site, from surface preparation to the final coat.
Related documents
Brochures and the catalog for the products used on this project.

Have a similar project?
Tell our team about your surface conditions and requirements.
or email sales@makepaint.co.id