Girder JPO Stasiun LRT-Mall Revo
Infrastructure · Bekasi · 2021
Project overview
Girder JPO Stasiun LRT-Mall Revo in Bekasi is a MAKEPaint project reference for structural steel.
- Location
- Bekasi
- Sector
- Infrastructure
- Project year
- 2021
- Duration
- 7 weeks
- Area
- ± 6,500 m²
- Surfaces
- Steel structures
- MAKEPaint products
- 3 products
Project photos
Photos from the project site, by coated surface.
Challenge, solution and result
The conditions on site, the coating system chosen, and how the work turned out.
Challenge
Exposed structural steel faces rain, humidity and industrial pollution that speed up corrosion, and the work had to go on without stopping activity around it.
Solution
A three-coat system for severe exposure: MAKE 303 FT zinc silicate primer at 65 µm, a MAKE 608 epoxy intermediate at 100 µm and a MAKE 700 polyurethane finish at 60 µm, 225 µm in total over SSPC SP 5/10.
Result
An area of about 6,500 m² was coated in 7 weeks. The thickness of every coat was checked on site before handover.
Coating system specification
The MAKEPaint products for each surface, from primer to finish, with the dry film thickness the application guide sets.
| Function | Product | DFT |
|---|---|---|
| Steel structuresSurface preparation: SSPC SP 5, 10 | ||
| Primer | PrimerMAKE 303Inorganic Zinc Silicate Primer | 65 µm |
| Intermediate | IntermediateMAKE 608Multipurpose HB Polyamide | 100 µm |
| Finish | FinishMAKE 700Aliphatic Polyurethane | 60 µm |
| Total dry film thickness | 225 µm | |
Project schedule
The stages of the work by week, from the site survey to handover.
Survey and surface tests
Week 1
The technical team checks the surface, the exposure and the area on site.
System recommendation
Weeks 1–2
The coating system and colors are agreed, with samples and technical data sheets.
Production and delivery
Weeks 2–3
The material is made and shipped from the MAKEPaint plant in Cikarang.
Preparation and application
Weeks 3–6
The surface is prepared, then primer, intermediate and finish coats go on.
Inspection and handover
Week 7
Coat thickness and adhesion are checked before the work is handed over.
Survey and surface tests
Week 1
The technical team checks the surface, the exposure and the area on site.
System recommendation
Weeks 1–2
The coating system and colors are agreed, with samples and technical data sheets.
Production and delivery
Weeks 2–3
The material is made and shipped from the MAKEPaint plant in Cikarang.
Preparation and application
Weeks 3–6
The surface is prepared, then primer, intermediate and finish coats go on.
Inspection and handover
Week 7
Coat thickness and adhesion are checked before the work is handed over.
Project video
Coating work on site, from surface preparation to the final coat.
Related documents
Brochures and the catalog for the products used on this project.

Have a similar project?
Tell our team about your surface conditions and requirements.
or email sales@makepaint.co.id