Loading MAKEPaint
Conceptual view of Dual Fuel Power Plant

Dual Fuel Power Plant

Energy and power · Timika · 2023

Project overview

Dual Fuel Power Plant in Timika is a MAKEPaint project reference for protective coating applications.

Location
Timika
Sector
Energy and power
Project year
2023
Duration
9 weeks
Area
± 11,500 m²
Surfaces
Protective coating
MAKEPaint products
3 products

Project photos

Photos from the project site, by coated surface.

Timika1 / 4
Coating applicationTimika · 2 / 4
Finished surfaceTimika · 3 / 4
Coat thickness checkTimika · 4 / 4

Challenge, solution and result

The conditions on site, the coating system chosen, and how the work turned out.

Challenge

Exposed structural steel faces rain, humidity and industrial pollution that speed up corrosion, and the work had to go on without stopping activity around it.

Solution

A three-coat system for severe exposure: MAKE 303 FT zinc silicate primer at 65 µm, a MAKE 608 epoxy intermediate at 100 µm and a MAKE 700 polyurethane finish at 60 µm, 225 µm in total over SSPC SP 5/10.

Result

An area of about 11,500 m² was coated in 9 weeks. The thickness of every coat was checked on site before handover.

Coating system specification

The MAKEPaint products for each surface, from primer to finish, with the dry film thickness the application guide sets.

Coating system specification
ProductDFT
Protective coatingSurface preparation: SSPC SP 5, 10
PrimerMAKE 303Inorganic Zinc Silicate Primer65 µm
IntermediateMAKE 608Multipurpose HB Polyamide100 µm
FinishMAKE 700Aliphatic Polyurethane60 µm
Total dry film thickness225 µm

Project schedule

The stages of the work by week, from the site survey to handover.

  1. Survey and surface tests

    Week 1

    The technical team checks the surface, the exposure and the area on site.

  2. System recommendation

    Weeks 1–2

    The coating system and colors are agreed, with samples and technical data sheets.

  3. Production and delivery

    Weeks 2–3

    The material is made and shipped from the MAKEPaint plant in Cikarang.

  4. Preparation and application

    Weeks 3–8

    The surface is prepared, then primer, intermediate and finish coats go on.

  5. Inspection and handover

    Week 9

    Coat thickness and adhesion are checked before the work is handed over.

Project video

Coating work on site, from surface preparation to the final coat.

Related documents

Brochures and the catalog for the products used on this project.

Have a similar project?

Tell our team about your surface conditions and requirements.

or email sales@makepaint.co.id