Ballroom Trust
Commercial buildings · Jakarta Pusat · 2021
Project overview
Ballroom Trust in Jakarta Pusat is a MAKEPaint project reference for building surfaces.
- Location
- Jakarta Pusat
- Sector
- Commercial buildings
- Project year
- 2021
- Duration
- 11 weeks
- Area
- ± 4,500 m²
- Surfaces
- Buildings and homes
- MAKEPaint products
- 3 products
Project photos
Photos from the project site, by coated surface.
Challenge, solution and result
The conditions on site, the coating system chosen, and how the work turned out.
Challenge
Building walls face rain, sun and humidity, while their color has to stay even and neat.
Solution
MAKE 101 P alkali primer for new walls, then two coats of MAKECOAT wall paint in a color from the MAKEPaint color card.
Result
An area of about 4,500 m² was coated in 11 weeks. The thickness of every coat was checked on site before handover.
Coating system specification
The MAKEPaint products for each surface, from primer to finish, with the dry film thickness the application guide sets.
| Function | Product | DFT |
|---|---|---|
| Buildings and homes | ||
| Primer | PrimerMAKE 101 PMAKE Alkali Primer | Per TDS |
| Finish | FinishMAKE 102MAKECOAT | Per TDS |
| Finish | FinishMAKE 103MAKEPROOF | Per TDS |
Project schedule
The stages of the work by week, from the site survey to handover.
Survey and surface tests
Week 1
The technical team checks the surface, the exposure and the area on site.
System recommendation
Weeks 1–2
The coating system and colors are agreed, with samples and technical data sheets.
Production and delivery
Weeks 2–3
The material is made and shipped from the MAKEPaint plant in Cikarang.
Preparation and application
Weeks 3–10
The surface is prepared, then primer, intermediate and finish coats go on.
Inspection and handover
Week 11
Coat thickness and adhesion are checked before the work is handed over.
Survey and surface tests
Week 1
The technical team checks the surface, the exposure and the area on site.
System recommendation
Weeks 1–2
The coating system and colors are agreed, with samples and technical data sheets.
Production and delivery
Weeks 2–3
The material is made and shipped from the MAKEPaint plant in Cikarang.
Preparation and application
Weeks 3–10
The surface is prepared, then primer, intermediate and finish coats go on.
Inspection and handover
Week 11
Coat thickness and adhesion are checked before the work is handed over.
Project video
Coating work on site, from surface preparation to the final coat.
Related documents
Brochures and the catalog for the products used on this project.

Have a similar project?
Tell our team about your surface conditions and requirements.
or email sales@makepaint.co.id